| County | Additional conditions 1-A1 | Additional conditions 1-A2 | Additional conditions 1-C2 |
|---|---|---|---|
| Adams | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Ashland | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Barron | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Bayfield | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Brown | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Buffalo | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Burnett | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Calumet | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Chippewa | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Clark | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Columbia | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | ER Review required. | ER Review required. |
| Crawford | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Dane | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
ER Review required. | ER Review required. |
| Dodge | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Door | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Douglas | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Dunn | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Eau Claire | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Florence | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Fond du Lac | No additional conditions. | No additional conditions. | No additional conditions. |
| Forest | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Grant | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Green | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Green Lake | No additional conditions. | No additional conditions. | No additional conditions. |
| Iowa | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. |
If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Iron | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Jackson | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Jefferson | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
| Juneau | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Kenosha | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
| Kewaunee | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
| La Crosse | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Lafayette | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Langlade | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Lincoln | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Manitowoc | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Marathon | For work on structures five or more stories in height, work shall not be conducted between March 1st and July 31st. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Marinette | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Marquette | No additional conditions. | No additional conditions. | No additional conditions. |
| Menominee | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Milwaukee | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
| Monroe | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Oconto | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Oneida | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Outagamie | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Ozaukee | For work on structures five or more stories in height, work shall not be conducted between March 1st and July 31st. | No additional conditions. | No additional conditions. |
| Pepin | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Pierce |
For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Polk | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Portage | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Price | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Racine | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
| Richland | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional comments |
| Rock | No additional conditions. | ER Review required. | ER Review required. |
| Rusk | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Sauk | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
ER Review required. | ER Review required. |
| Sawyer | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Shawano | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Sheboygan | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
| St. Croix | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Taylor | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | No additional conditions. |
| Trempealeau | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Vernon | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Vilas | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Walworth | No additional conditions. | No additional conditions. | No additional conditions. |
| Washburn | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Washington | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
| Waukesha | No additional conditions. | No additional conditions. | No additional conditions. |
| Waupaca | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Waushara | No additional conditions. | No additional conditions. | No additional conditions. |
| Winnebago | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
| Wood | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |